Drivers, pedestrians, and bicyclists are urged to use extra caution when traveling through the work zone.

To minimize impacts on the traveling public, the contractor will be working during the weekend, from Friday, October 23 to Monday, October 26. Motorists should anticipate the following lane closures at the intersection of Corkscrew Road and Alico Road for crews to work on reconstructing the roadway:

    • Nightly lane closures will be in place on Corkscrew Road during the nighttime/overnight hours of 8 p.m. to 5 a.m.
    • Northbound and southbound Alico Road will be reduced to one lane throughout the entire duration of the work.
    • Motorists are encouraged to seek alternate routes during this time to aid the flow of traffic through the area. Flaggers and law enforcement will be onsite to assist with traffic control.

Crews will be paving on the north side of Corkscrew Road from the main entrance of Corkscrew Shores to Alico Road during daytime hours. Please use extra caution as trucks will be entering and exiting the roadway.

Crews will be installing the curb throughout the project.

Crews will be grading the road base on the north side of Corkscrew Road, close to the existing road. Please follow all signage and directions of flaggers.

Crews will be working on or near the sidewalk on the south side of Corkscrew Road to complete street lighting work and other items. Cones will be set up as necessary to redirect pedestrians.

Crews will be installing drainage throughout the project area on Corkscrew Road and Alico Road. Motorists should expect trucks and equipment to be moving materials throughout the project.

Motorists should drive with caution and expect intermittent daytime flagging as road crews are performing earthwork up to the shoulders of the road on Corkscrew Road and Alico Road, within the project limits. Please be aware that trucks may be entering and leaving the roadway.

Crews will be installing utility conduits, light pole bases and light poles on the north side of Corkscrew Road from Wayside Lane to Alico Road.

The work activities above are scheduled to occur, however unforeseen underground conditions and weather may affect this schedule.

Please use caution and watch for workers and construction vehicles entering and leaving the roadway. Due to additional work required by Lee County Utilities, as well as delays in utility relocations by FPL and Lumen, the project completion is expected late Spring 2027. Project cost is approximately $27 M. The contractor is Bergeron Land Development, Inc. For further questions, please visit the project website at https://corkscrewroadwidening.com or contact Jennifer Dorning by email at Jennifer.Dorning@atkinsrealis.com or by phone at (239) 338-7723.