PURPOSE: Identify environmental risks that could impact the Village of Estero and provide recommendations to mitigate those risks.

Project Summary

  • Request for Qualifications Issued: December 3, 2024
  • Firms Evaluations: March 4, 2026
  • Contract Approved by Village Council: August 15, 2025

Project Cost: $495,500

Grant Funding: $450,000

Project Team:

APTIM Environmental & Infrastructure
Samantha Danchuk, Ph.D., P.E. – Project Manager
Cigdem Ozkan, Ph.D., P.E. – Resilience Project Manager
Alireza Kazemian, Ph.D. – Climate & Coastal Resilience Engineer
Lara Wakefield – Risk Management Specialist

Lago Consulting

Marcelo Lago, Ph.D. – Lead Stormwater Modeling

AIM Engineering

Daniel Schroeder, P.E. – Stormwater

Public Meeting No. 01: October 8, 2025
Public Meeting No. 02: February 25, 2026

Final Public Presentation Video at right.