Broadway Avenue WestCrews from JP Murphy Construction will be replacing the drainage pipe under Broadway Avenue West, located between Logan Avenue and Poinciana Avenue.

Construction is expected to start the week of June 11, 2018, and last approximately two weeks.

The existing metal pipe has reached the end of its service life and is being replaced by a larger concrete pipe. The new pipe will help improve drainage in the area.

The roadway will remain open during construction. But, please expect some delays as one lane will be closed at times.

Please contact the Village of Estero’s Public Works at 239-221-5035 with any questions.